Headquarters Project - Owen County, IN

Environmental Assessment

Finding of No Significant Impact

Hoosier Energy intends to request financing from the USDA Rural Utilities Service (RUS) for the proposed Headquarters Project in Monroe County, Indiana. RUS’s Environmental Assessment (EA) for the proposed project was available for thirty days for public review and comment following the publication of the Notice of Availability in the newspaper on April 3, 2012. RUS executed a Finding of No Significant Impact for the project on May 23, 2013.

To obtain additional information please contact Emily Orler, Environmental Protection Specialist. Ms. Orler may be reached at 202-720-1414; emily.orler@wdc.usda.gov; or Rural Utilities Service, 1400 Independence Ave., SW, Mail Stop 1571, Washington, DC 20250.