(1) Biomass, bioenergy. The technical requirements specified in paragraphs (d)(1)(i) through (x) apply to renewable energy projects that produce fuel, thermal energy, or electric power from a biomass source, including wood, agricultural residue excluding animal wastes, or other energy crops considered biomass or bioenergy projects. The major components of bioenergy systems will vary significantly depending on the type of feedstock, product, type of process, and size of the process but in general includes components around which the balance of the system is designed.
(i) Qualifications of project team. The biomass project team will vary according to the complexity and scale of the project. For engineered systems, the project team should consist of a system designer, a project manager, an equipment supplier, a project engineer, a construction contractor or system installer, and a system operator and maintainer. One individual or entity may serve more than one role.
The project team must have demonstrated expertise in similar biomass systems development, engineering, installation, and maintenance. The Applicant must provide authoritative evidence that project team service providers have the necessary professional credentials or relevant experience to perform the required services. The Applicant must also provide authoritative evidence that vendors of proprietary components can provide necessary equipment and spare parts for the system to operate over its design life. The application must:
(A) Discuss the proposed project delivery method. Such methods include a design, bid, build where a separate engineering firm may design the project and prepare a request for bids and the successful bidder constructs the project at the Applicant’s risk, and a design build method, often referred to as turn key, where the Applicant establishes the specifications for the project and secures the services of a developer who will design and build the project at the developer’s risk;
(B) Discuss the biomass system equipment manufacturers of major components being considered in terms of the length of time in business and the number of units installed at the capacity and scale being considered;
(C) Discuss the project manager, equipment supplier, system designer, project engineer, and construction contractor qualifications for engineering, designing, and installing biomass energy systems including any relevant certifications by recognized organizations or bodies. Provide a list of the same or similar projects designed, installed, or supplied and currently operating and with references if available; and
(D) Describe the system operator’s qualifications and experience for servicing, operating, and maintaining biomass renewable energy equipment or projects. Provide a list of the same or similar projects designed, installed, or supplied and currently operating and with references if available.
(ii) Agreements and permits. The Applicant must identify all necessary agreements and permits required for the project and the status and schedule for securing those agreements and permits, including the items specified in paragraphs (d)(1)(ii)(A) through (G).
(A) Biomass systems must be installed in accordance with applicable local, State, and national codes and regulations. Identify zoning and code issues, and required permits and the schedule for meeting those requirements and securing those permits.
(B) Identify licenses where required and the schedule for obtaining those licenses.
(C) Identify land use agreements required for the project and the schedule for securing the agreements and the term of those agreements.
(D) Identify any permits or agreements required for solid, liquid, and gaseous emissions or effluents and the schedule for securing those permits and agreements.
(E) Identify available component warranties for the specific project location and size.
(F) Systems interconnected to the electric power system will need arrangements to interconnect with the utility. Identify utility system interconnection requirements, power purchase arrangements, or licenses where required and the schedule for meeting those requirements and obtaining those agreements. This is required even if the system is installed on the customer side of the utility meter. For systems planning to utilize a local net metering program, describe the applicable local net metering program.
(G) Describe all potential environmental impacts resulting from siting issues, construction and operation of the proposed project. Identify other site or design alternatives that were considered in your planning process. Identify all environmental compliance issues such as required permits (i.e. wetland fill, endangered species, air quality, NPDES, etc.)
(iii) Resource assessment. The Applicant must provide adequate and appropriate evidence of the availability of the renewable resource required for the system to operate as designed. Indicate the type, quantity, quality, and seasonality of the biomass resource including harvest and storage, where applicable. Where applicable, also indicate shipping or receiving method and required infrastructure for shipping. For proposed projects with an established resource, provide a summary of the resource.
(iv) Design and engineering. The Applicant must provide authoritative evidence that the system will be designed and engineered so as to meet its intended purpose and need, will ensure public safety, mitigate any adverse environmental impacts, and will comply with applicable laws, regulations, agreements, permits, codes, and standards. Projects shall be engineered by a qualified entity. Systems must be engineered as a complete, integrated system with matched components. The engineering must be comprehensive including site selection, system and component selection, and system monitoring equipment. Systems must be constructed by a qualified entity.
(A) The application must include a concise but complete description of the biomass project including location of the project, resource characteristics, system specifications, electric power system interconnection, and monitoring equipment. Identify possible vendors and models of major system components. Describe the expected electric power, fuel production, or thermal energy production of the proposed system as rated and as expected in actual field conditions. For systems with a capacity more than 20 tons per day of biomass, address performance on a monthly and annual basis. For small projects such as a commercial biomass furnace or pelletizer of up to 5 tons daily capacity, proven, commercially available devices need not be addressed in detail. Describe the uses of or the market for electricity, heat, or fuel produced by the system. Discuss the impact of reduced or interrupted biomass availability on the system process.
(B) The application must include a description of the siting criteria used in selecting the project site and the reason for elimination of other site alternatives considered and address issues such as site access, foundations, backup equipment when applicable, and environmental issues with emphasis on land use, air quality, water quality, noise pollution, soil degradation, wildlife, habitat fragmentation, aesthetics, odor, and other construction and installation issues applicable to this type of technology. Identify any unique construction and installation issues.
(C) Sites must be controlled by the agricultural producer or small business for the proposed project life or for the financing term of any associated federal loans or loan guarantees.
(v) Project development schedule. The Applicant must identify each significant task, its beginning and end, and its relationship to the time needed to initiate and carry the project through startup and shakedown. Provide a detailed description of the project timeline including resource assessment, system and site design, permits and agreements, equipment procurement, and system installation from excavation through startup and shakedown.
(vi) Financial feasibility. The Applicant must provide a study that describes costs and revenues of the proposed project to demonstrate the financial performance of the project. Provide a detailed analysis and description of project costs including project management, resource assessment, project design, project permitting, land agreements, equipment, site preparation, system installation, startup and shakedown, warranties, insurance, financing, professional services, and operations and maintenance costs. Provide a detailed analysis and description of annual project revenues and expenses. Provide a detailed description of applicable investment, productivity, tax, loan, and grant incentives.
(vii) Equipment procurement. The Applicant must demonstrate that equipment required by the system is available and can be procured and delivered within the proposed project development schedule. Biomass systems may be constructed of components manufactured in more than one location. Provide a description of any unique equipment procurement issues such as scheduling and timing of component manufacture and delivery, ordering, warranties, shipping, receiving, and on-site storage or inventory. Procurement must be made in accordance with the requirements of 7 CFR part 3015.
(viii) Equipment installation. The Applicant must fully describe the management of and plan for site development and system installation, provide details regarding the scheduling of major installation equipment needed for project construction, and provide a description of the startup and shakedown specification and process and the conditions required for startup and shakedown for each equipment item individually and for the system as a whole.
(ix) Operations and maintenance. The Applicant must identify the operations and maintenance requirements of the system necessary for the system to operate as designed over the design life. The Applicant must:
(A) Provide information regarding available system and component warranties and availability of spare parts;
(B) For systems having a biomass input capacity exceeding 10 tons of biomass per day,
(1) Describe the routine operations and maintenance requirements of the proposed system, including maintenance schedule for the mechanical, piping, and electrical systems and system monitoring and control requirements. Provide information that supports expected design life of the system and timing of major component replacement or rebuilds; and
(2) Discuss the costs and labor associated with operations and maintenance of system and plans for in or outsourcing. Describe opportunities for technology transfer for long term project operations and maintenance by a local entity or owner/operator; and
(C) Provide and discuss the risk management plan for handling large, unanticipated failures or major components. Include in the discussion, costs and labor associated with operations and maintenance of system and plans for insourcing or outsourcing.
(x) Decommissioning. When uninstalling or removing the project, describe the decommissioning process. Describe any issues, any environmental compliance requirements, and costs for removal and disposal of the system.