(3) Geothermal, electric generation. The technical requirements specified in paragraphs (d)(3)(i) through (x) apply to geothermal projects that produce electric power from the thermal potential of a geothermal source. The major components of an electric generating geothermal system include the production well, the separator or heat exchanger, the turbine, the generator, condenser, and the balance of station elements including the, field piping, roads, fencing and grading, plant buildings, transformers and other electrical infrastructure such as interconnection equipment.
(i) Qualifications of project team. The electric generating geothermal plant project team should consist of a system designer, a project manager, an equipment supplier, a project engineer, a construction contractor, and a system operator and maintainer. One individual or entity may serve more than one role.
The project team must have demonstrated expertise in geothermal electric generation systems development, engineering, installation, and maintenance. The Applicant must provide authoritative evidence that project team service providers have the necessary professional credentials or relevant experience to perform the required services. The Applicant must also provide authoritative evidence that vendors of proprietary components can provide necessary equipment and spare parts for the system to operate over its design life. The Applicant must:
(A) Discuss the proposed project delivery method. Such methods include a design, bid, build where a separate engineering firm may design the project and prepare a request for bids and the successful bidder constructs the project at the Applicant’s risk, and a design build method, often referred to as turn key, where the Applicant establishes the specifications for the project and secures the services of a developer who will design and build the project at the developer’s risk;
(B) Discuss the geothermal plant equipment manufacturers of major components being considered in terms of the length of time in business and the number of units installed at the capacity and scale being considered;
(C) Discuss the project manager, equipment supplier, system designer, project engineer, and construction contractor qualifications for engineering, designing, and installing geothermal electric generation systems including any relevant certifications by recognized organizations or bodies. Provide a list of the same or similar projects designed, installed, or supplied and currently operating and with references if available; and
(D) Describe system operator’s qualifications and experience for servicing, operating, and maintaining electric generating geothermal projects. Provide a list of the same or similar projects designed, installed, or supplied and currently operating and with references if available.
(ii) Agreements and permits. The Applicant must identify all necessary agreements and permits required for the project and the status and schedule for securing those agreements and permits, including the items specified in paragraphs (d)(3)(ii)(A) through (F).
(A) Electric generating geothermal systems must be installed in accordance with applicable local, State, and national codes and regulations. Identify zoning and code issues, and required permits and the schedule for meeting those requirements and securing those permits.
(B) Identify any permits or agreements required for well construction and for disposal or re-injection of cooled geothermal waters and the schedule for securing those agreements and permits.
(C) Identify land use or access to the resource agreements required for the project and the schedule for securing the agreements and the term of those agreements.
(D) Identify available component warranties for the specific project location and size.
(E) Systems interconnected to the electric power system will need arrangements to interconnect with the utility. Identify utility system interconnection requirements, power purchase arrangements, or licenses where required and the schedule for meeting those requirements and obtaining those agreements.
(F) Describe all potential environmental impacts resulting from siting issues, construction and operation of the proposed project. Identify other site or design alternatives that were considered in your planning process. Identify all environmental compliance issues such as required permits (i.e. wetland fill, endangered species, Air Quality, State Water Quality Certification, etc.)
(iii) Resource assessment. The Applicant must provide adequate and appropriate evidence of the availability of the renewable resource required for the system to operate as designed. Indicate the quality of the geothermal resource including temperature, flow, and sustainability and what conversion system is to be installed. Describe any special handling of cooled geothermal waters that may be necessary. Describe the process for determining the geothermal resource including measurement setup for the collection of the geothermal resource data. For proposed projects with an established resource, provide a summary of the resource and the specifications of the measurement setup.
(iv) Design and engineering. The Applicant must provide authoritative evidence that the system will be designed and engineered so as to meet its intended purpose and need, will ensure public safety, mitigate any adverse environmental impacts, and will comply with applicable laws, regulations, agreements, permits, codes, and standards. Projects shall be engineered by a qualified entity. Systems must be engineered as a complete, integrated system with matched components. The engineering must be comprehensive including site selection, system and component selection, conversion system component and selection, design of the local collection grid, interconnection equipment selection, and system monitoring equipment. Systems must be constructed by a qualified entity.
(A) The application must include a concise but complete description of the geothermal project including location of the project, resource characteristics, thermal system specifications, electric power system interconnection equipment and project monitoring equipment. Identify possible vendors and models of major system components. Provide the expected system energy production on a monthly and annual basis.
(B) The application must include a description of the siting criteria used in selecting the project site and the reason for elimination of other site alternatives considered and address issues such as site access, foundations, backup equipment when applicable, proximity to the electrical grid, environmental issues with emphasis on land use, air quality, water quality, noise pollution, soil degradation, wildlife, habitat fragmentation, aesthetics, odor, and other construction, and installation issues applicable to this type of technology. Identify any unique construction and installation issues.
(C) Sites must be controlled by the agricultural producer or small business for the proposed project life or for the financing term of any associated federal loans or loan guarantees.
(v) Project development schedule. The Applicant must identify each significant task, its beginning and end, and its relationship to the time needed to initiate and carry the project through startup and shakedown. Provide a detailed description of the project timeline including resource assessment, system and site design, permits and agreements, equipment procurement, and system installation from excavation through startup and shakedown.
(vi) Financial feasibility. The Applicant must provide a study that describes costs and revenues of the proposed project to demonstrate the financial performance of the project. Provide a detailed analysis and description of project costs including project management, resource assessment, project design, project permitting, land agreements, equipment, site preparation, system installation, startup and shakedown, warranties, insurance, financing, professional services, and operations and maintenance costs. Provide a detailed analysis and description of annual project revenues including electricity sales, production tax credits, revenues from green tags, and any other production incentive programs throughout the life of the project. Provide a detailed description of applicable investment incentives, productivity incentives, loans, and grants.
(vii) Equipment procurement. The Applicant must demonstrate that equipment required by the system is available and can be procured and delivered within the proposed project development schedule. Geothermal systems may be constructed of components manufactured in more than one location. Provide a description of any unique equipment procurement issues such as scheduling and timing of component manufacture and delivery, ordering, warranties, shipping, receiving, and on-site storage or inventory. Procurement must be made in accordance with the requirements of 7 CFR part 3015.
(viii) Equipment installation. The Applicant must fully describe the management of and plan for site development and system installation, provide details regarding the scheduling of major installation equipment needed for project construction, and provide a description of the startup and shakedown specification and process and the conditions required for startup or shakedown for each equipment item individually and for the system as a whole.
(ix) Operations and maintenance. The Applicant must identify the operations and maintenance requirements of the system necessary for the system to operate as designed over the design life. The Applicant must:
(A) Ensure that systems must have at least a 3-year warranty for equipment. Provide information regarding turbine warranties and availability of spare parts;
(B) Describe the routine operations and maintenance requirements of the proposed project, including maintenance for the mechanical and electrical systems and system monitoring and control requirements;
(C) Provide information that supports expected design life of the system and timing of major component replacement or rebuilds;
(D) Provide and discuss the risk management plan for handling large, unanticipated failures of major components such as the turbine. Include in the discussion, costs and labor associated with operations and maintenance of system and plans for insourcing or outsourcing; and
(E) Describe opportunities for technology transfer for long term project operations and maintenance by a local entity or owner/operator.
(x) Decommissioning. When uninstalling or removing the project, describe the decommissioning process. Describe any issues, any environmental compliance requirements, and costs for removal and disposal of the system.