
Shouldering the risk
Strategy for risk management essential to moving
cellulosic technology forward
By Anthony Crooks, Agricultural Economist
USDA Rural Development
n his 2007 State of the Union Address,
President George W. Bush emphasized the
need to increase alternative fuel production
to 35 billion gallons by 2017, or nearly five
times the original target of 7.5 billion gallons
(see sidebar). To meet this goal, the commercial-scale
conversion of biomass feedstocks into ethanol, and primarily
cellulose to ethanol, will play a prominent role. This effort
will create more opportunities for producer-owned co-ops
and LLCs to become biofuel producers.
To date, there are still no commercial-scale cellulose-toethanol
facilities in operation. The risks and uncertainties of
these still unproven technologies are significant.
Breakthroughs in new technologies continue to develop
along multiple fronts to reach commercialization. A
partnership of technical expertise and the financial
wherewithal from both private and public sectors is required
to bridge the developmental gaps and to distribute the
startup risks.
Financing represents the greatest hurdle for an unproven
technology. This article describes the difficulties involved
with the financing of unproven technologies and describes
the significant partnerships now arising to direct the
evolution of the cellulose-to-ethanol industry.
Financing unproven technologies
Twenty-five years of industry experience has helped
ethanol industry lenders and financial backers to become well
acquainted with the risks associated with ethanol projects.
The risks of these projects typically involve a traditional
power plant, burning either natural gas or coal, and a wellproven
process technology. However, cellulosic ethanol
plants that will soon compete for financing will use
equipment and/or process technologies that have little or no
commercial operating history.
Unproven technology risks embrace all phases of a new
project: construction and startup as well as operations. Of
particular concern after a plant begins to operate at capacity
is ‘conversion risk,’ the relative efficiency at which the plant
is operating. Lenders are rightfully concerned that cuttingedge
technologies operate at state-of-the-art efficiency, and
particularly so if their exposure is substantially greater than it
would be with a proven technology. But, if it can be
independently certified that the plant can operate at a level
sufficient to repay the debt plus some risk margin, lenders
may be persuaded to assume a portion of the conversion risk.
Biofuels lenders who understand the history of the
industry may have fewer concerns about conversion risk.
Typically, once an ethanol project operates successfully for a
couple of years, it’s very likely that it will continue to do so.
Consequently, lenders now tend to focus more on the
technology risks involved with construction and startup
phases of a project, and less so on operations.
Because cellulosic ethanol has no commercial operating
history, there is an element of technology risk that cannot be
assessed. Further, in the absence of a track record, lenders
will want to see if the project has demonstrated success on a
smaller scale. In other words: How successful is the pilot
plant or the demonstration plant?
Unlike a pilot plant, a demonstration plant uses a
continuous process on an industrial scale. A demonstration
plant is usually a necessary stepping stone from a pilot plant
to a commercial-scale facility. It’s very difficult to leapfrog
from a 500-gallon tank to building a 20- or 50-million-gallon
biorefinery. Moving from a successful demonstration plant to
the next level involves finding a construction contractor
willing to assume the risk that the demonstration plant can be
replicated on a commercial scale.
A related challenge confronting cellulosic ethanol is the
absence of a traditional engineering, procurement and
construction (EPC) contractor. The EPC is a contractual
arrangement signed by the builder and technology provider
to guarantee the plant’s timely delivery and performance to
specifications. The contract is necessary to plant developers
as they attempt to obtain financing.
The “full wrap”
Building a traditional ethanol plant involves working with
one of the small handful of process providers that offer turnkey
design and construction services under a design-build
contract. The contract covers the process provider's core
technology and the "balance of plant," which often includes
every plant system, from grain receiving to fuel storage and
all points in between. The process provider is then
responsible for ensuring that the fully integrated plant is
constructed on time to contract specifications and is fully
operational at the specified (nameplate) production capacity.
This engineering, procurement and contracting agreement is
known commonly as a "full wrap."
But as industry expansion strains the ability of most
process providers to supply
full-wrap services, many
technology firms are
shifting away from active
involvement in design and
construction. Firms now
focus instead on licensing
their core technologies and
leave the design and
construction of the facility
to third-party engineers and
contractors. The
responsibility and risk of
ensuring that all of the
disparate systems, buildings
and equipment fit together
into an integrated operating
facility now lie with the
owner.
An EPC for a cellulosic
plant must embrace
elements of conversion risk
that protect against
inadequate throughput
efficiency. Also, liquidated
damages (see below) will
need to be assessed to repay
the debt should the project
fail to operate as
contractually specified.
Lenders and private
equity funds prefer to back
an “early development”
project — a single unproven
technology or process that is
part of a system of proven
technologies — rather than
a “revolutionary” system.
However, with the
appropriate guarantees (and
sufficient reserves), the
uncertain elements of the
unproven technology can be
“wrapped” in with the final
performance of the project
and proven technologies.
Revolutionary systems are ideally small-scale venture
capital investments that range from $5 million to $7 million,
rather than large project transactions that involve a 20-year
payout. Generally, the limit for venture capital is about $50
million and requires a 25- to 30-percent return on
investment. There is another
rub for cellulosic ethanol.
For even a relatively modest,
commercial-scale cellulosic
ethanol biorefinery of 25 to
40 million gallons per year,
capacity is expected to cost
upwards of $300 million.
Expecting quick returns
However, perhaps an even
greater problem with
venture capital financing of a
cellulosic project is the
expectation of a quicker
return. A venture capitalist
expects a technology
investment to be a means to
build a company and gain
significant value from the
relatively quick selling of
either many units of the
business, or the entire
business itself. This
expectation lies in sharp
contrast with a private
equity investor in energy or
infrastructure who looks for
a return from business
operations over an extended
period of time.
So, unless a cellulosic plant
is financed entirely from
equity, at levels far exceeding
those that traditional venture
capital sources will support,
an equity investor will expect
a lender to finance
construction. Otherwise, it
will be difficult to persuade
the equity fund to provide
developmental capital.
A financing impasse can
result. Lenders refuse to
assume risk on unproven
technologies and equity
funds won’t provide funding unless a lender will finance
construction.
An alternative approach might be to separate the unproven
elements from the rest of the project. The proven portion of
the project might then be financed using traditional sources
and the unproven portion using equity. Overall, the project is
a blend of equity and traditional project financing.
A problem with this approach, however, is that equity
stands in line behind any debt should the project fail and go
to foreclosure or liquidation. The challenge with this
structure is to provide a return with a reasonable risk
premium, given the enormous scale of the project. Apart
from the federal government or a deeply-pocketed
construction contractor to guarantee performance, such a
project is very unlikely to secure private equity funding.
Liquidated damages, related issues
One way to get past the technology risk issue might be to
negotiate with the contractor or the equipment vendor to
assume the risk and pay the risk bearer in the form of
liquidated damages. Damages are said to be liquidated when
the amount of damages recoverable in the event of a specified
contract breach (for example, late performance at
construction, or inefficient performance at conversion) is
agreed at a specified date.
Two conditions must be met to uphold liquidated
damages. First, the amount of the damages identified must
roughly approximate the damages likely to be incurred by the
party seeking relief in the event of failure. Second, damages
must be sufficiently uncertain at the time the contract is
made that both parties recognize the significant benefit of
being spared any future difficulty of estimating those
damages.
Liquidated damages for construction risk are generally
written to account sufficiently for each phase of construction
risk: mechanical completion, substantial completion and final
completion. Liquidated damages for mechanical completion,
when the plant is fully ready to start operations, should be no
less than the complete cost of construction. Otherwise, the
exposure to investors is too great.
Liquidated damages for substantial completion, where the
plant is demonstrated to fully work at a specified target
capacity — 50 percent, for example — ranges from 10 to 20
percent of construction costs. Final completion involves the
plant fully operating at the nameplate capacity specified in
the contract, and generally requires liquidated damages of
not less than 10 percent.
Other ways to allocate risk
Suppose, however, that a project is sufficiently interesting
for a venture capitalist and a lender to consider financing, but
the lender is unwilling to assume the technology risk. A
project finance expert can parcel out, or deconstruct, and
distribute the risks of a project among many takers: insurance
providers, ethanol or specialty product marketers, sponsors,
construction contractors and technology licensors.
Generally, however, it’s the construction contractor, equity
provider and — on rare occasions — the technology
providers that are the principle risk takers in a project. While
insurance providers have also attempted to wrap the risk of
new technologies into projects, insurance is generally
considered ineffective protection because of the gaps in
coverage. Moreover, a performance bond on a construction
contract is significantly easier to collect than an insurance
contract which may have many outs.
Federal government role
Many are looking to the federal government to assume a
significant part of the risk in developing renewable energy
technology. This expectation is being fulfilled in the
proposed Farm Bill, which includes billions of dollars for
renewable energy (see sidebar), and by a $2.1 billion
guaranteed loan program under the U.S. Department of
Energy. To qualify for loan guarantees under this program, a
project must meet two basic requirements:
- It must avoid, reduce or sequester pollutants and
gases, and
- It must use new, or significantly improved,
technologies when compared to those in general use
in the marketplace.
However, lenders have been loath to participate in the
program because the guarantees are structured to put the
lender in the “first-loss” position in the event of foreclosure.
The government guarantee is for up to 80 percent.
Because the U.S. government takes the first lien on the
project, a lender would be left with a second lien for the nonguaranteed
20 percent of the loan value. For a $400 million
loan, 20 percent is not an insignificant
sum. So a lender has a major exposure if
there is a liquidation.
The guidelines also require that both
guaranteed and non-guaranteed
portions of a loan be traded together in
secondary markets. So where lenders
often desire to sell the guaranteed
portion of a note on a facility, selling
just the guaranteed portion appears not
to be an option. While the guidelines
left unexplained what would happen if
this condition were breached, it could
lead to inability to enforce the loan
guarantee. Opportunities to restructure
the risk into a package of wraps and/or
strips thus appear unavailable. The
intent of the program may have been to
encourage lenders to finance projects
with unproven technologies, but its
impact had the opposite effect.
The U.S. Department of Energy
(DOE) recently announced that is
investing up to $385 million for six
biorefinery projects over the next four
years (see sidebar, page 17). Each award
is equivalent to a 20-percent equity
stake. With these awards and the
pending guaranteed loans that follow,
the federal government will not only
guarantee the loans on the projects, it
will also assume the first loss in the
event of foreclosure.
Given the scale of investment and
the role of intellectual property in
cellulosic ethanol, the farmer-owned
business model may struggle to find its
place in this emerging segment of the
industry. However, as cellulosic
technologies become proven, producerowned
businesses may to be launched
— or existing ones expanded — to
produce cellulosic ethanol under some
forms of licensing arrangements.
In four of these six plants, farmers
will produce the main source of
cellulosic feedstock necessary to
produce ethanol. It may be possible,
therefore, for farmers to negotiate a
place in the ownership structure for
themselves. Broin Companies’ system of
partnering with farmers and rural
investors seems very adaptable to tie
together capital, intellectual property
and feedstock sourcing.
The DOE solicitation, announced
about one year ago, was initially for
$160 million for three biorefineries.
However, in an effort to expedite the
goals of President Bush’s “Advanced
Energy Initiative” and “Twenty-in-Ten-
Initiative” (which aim to increase the
use of renewable and alternative fuels in
the transportation sector to the
equivalent of 35 billion gallons of
ethanol a year by 2017) Energy
Secretary Bodman raised the funding
ceiling.
“We had a number of very good
proposals, but these six were considered
‘meritorious’ by a review panel of
bioenergy experts,” Bodman said.
Biorefinery projects
awarded $385 million
The U.S. Department of Energy recently awarded $385
million in funds for six biorefineries developing technology
for creation of cellulosic ethanol. Combined with the industry
cost share, more than $1.2 billion is expected to be invested
in these six biorefineries.
- Abengoa Bioenergy Biomass of Kansas LLC, Chesterfield,
Mo., will receive up to $76 million. The proposed
plant will be located in Kansas and produce 11.4 million
gallons of ethanol annually and enough energy to power
the facility. Any excess energy will be used to power the
adjacent corn dry grind mill. The plant will use 700 tons
per day of corn stover, wheat straw, milo stubble,
switchgrass and other feedstocks. Investors/participants
include: Abengoa Bioenergy R&D Inc.; Abengoa
Engineering and Construction LLC; Antares Corp.; and
Taylor Engineering.
- ALICO Inc., La Belle, Fla., will receive up to $33 million.
The proposed plant will be in LaBelle (Hendry County),
Fla., and will produce 13.9 million gallons of ethanol a
year and 6,255 kilowatts of electric power, as well as 8.8
tons of hydrogen and 50 tons of ammonia per day. For
feedstock, the plant will use 770 tons per day of yard,
wood and vegetative wastes and, eventually, energy
cane (sugar). Investors and participants include: Bioengineering
Resources Inc. of Fayetteville, Ark.; Washington
Group International of Boise, Idaho; GeoSyntec
Consultants of Boca Raton, Fla.; BG Katz Companies/
JAKS LLC of Parkland, Fla.; and Emmaus Foundation Inc.
- BlueFire Ethanol Inc., Irvine, Calif., will receive up to $40
million. The proposed plant will be in Southern California,
sited on an existing landfill and will produce about
19 million gallons of ethanol annually. For feedstock, the
plant would use 700 tons per day of sorted green waste
and wood waste from landfills. Investors/participants
include: Waste Management Inc.; JGC Corporation;
MECS Inc.; NAES; and PetroDiamond.
- Broin Companies of Sioux Falls, S. D., up to $80 million.
The plant is in Emmetsburg (Palo Alto County), Iowa,
and after expansion, it will produce 125 million gallons
of ethanol per year, of which roughly 25 percent will be
cellulosic ethanol. For feedstock in the production of
cellulosic ethanol, the plant expects to use 842 tons per
day of corn fiber, cobs and stalks. Participants include:
E. I. du Pont de Nemours and Company; Novozymes
North America Inc.; and DOE National Renewable Energy
Laboratory.
- Iogen Biorefinery Partners LLC, of Arlington, Va., will
receive up to $80 million. The proposed plant will be
built in Shelley, Idaho, near Idaho Falls, and will produce
18 million gallons of ethanol annually. The plant will use
700 tons per day of agricultural residues, including
wheat straw, barley straw, corn stover, switchgrass,
and rice straw as feedstocks. Investors/partners
include: Iogen Energy Corp.; Iogen Corp.; Goldman
Sachs; and The Royal Dutch/Shell Group.
- Range Fuels (formerly Kergy Inc.) of Broomfield, Colo.,
will receive up to $76 million. The proposed plant will be
constructed in Soperton (Treutlen County), Ga., and will
produce about 40 million gallons of ethanol and 9 million
gallons of methanol annually. As feedstock, the plant will
use 1,200 tons per day of wood residues and wood
based energy crops. Investors/participants include:
Merrick and Co.; PRAJ Industries Ltd.; Western
Research Institute; Georgia Forestry Commission; Yeomans
Wood and Timber; Treutlen County Development
Authority; BioConversion Technology; Khosla Ventures;
CH2MHill; Gillis Ag and Timber.
Farm Bill supports cellulosic
ethanol development
Agriculture Secretary Mike Johanns says the Administration's
new Farm Bill proposal would dramatically expand
the federal commitment to renewable fuels. He notes that a
series of Farm Bill forums showed “real excitement about
renewable energy” and the new funding it provides for
renewable energy research, development and production
— much of it targeted to cellulosic ethanol.
The Farm Bill would establish a program to invest $25
million a year for four years for incentives to encourage the
development and expansion of cellulosic ethanol production.
In addition, the BioPreferred Program would be reauthorized
and would provide $18 million over 10 years to
expand the use of biobased products by the federal government
and to speed the development and adoption of
these products in the private sector.
Among other energy provisions of the Farm Bill are
measures to:
- Include a biomass reserve within the Conservation
Reserve Program (CRP), under the proposed Conservation
legislation.
- Reauthorize the Renewable Energy Systems and Energy
Efficiency Improvements grants, loan and loan guarantee
programs to provide an estimated $2.17 billion of cellulosic
ethanol loan guarantees and $500 million for grants,
under the proposed Rural Development legislation.
- Revise the Biomass Research and Development Act of
2000, providing $150 million for grants focusing on cellulosic
ethanol production, under the proposed Rural
Development legislation.
- Include a Bioproducts Research Initiative, providing $500
million in grants to increase the cost-effectiveness of
bioenergy, in the proposed Research legislation.
- Provide $150 million for Forest Service research into better
ways to use woody biomass for the production of
bioenergy, in the proposed Forestry legislation.