Predevelopment work nets higher
royalties for landowners

By Dan Campbell, Editor



f any place on earth was made to order for a wind farm, Trimont, Minn., would seem to be it. Not only do prairie winds blow here most of the year, but a major power transmission line runs through the area and there is a nearby electric peaking plant (which kicks into service during periods of peak energy demand).

So when Great River Energy — an electricity generation and transmission co-op – put out a proposal in 2003 soliciting bids from anyone wanting to supply it with 100 megawatts of renewable energy, it got Neal Von Ohlen and some other area farmers thinking very seriously about developing a community-owned wind farm.

“We drew a big square (encompassing about 16.5 square miles) around the peaking plant and focused on getting those landowners to join in an LLC,” says Von Ohlen, who farms about 1,700 acres of corn and soybeans with his father and brother.

The farmers then hired a consultant to pursue a project that they hoped would result in the first large-scale, farmer-owned wind farm in Minnesota, says Von Ohlen, standing in the driveway of his farm, nearly in the shadow of a turbine that seems to sprout from his grain bins.

They were told the logistics looked good, so 50 area landowners formed Trimont Area Wind Farm LLC (TAWF). At that point, they had only about three weeks to pull their proposal together and get it to Great River Energy. They managed to meet the April 30 deadline, but TAWF was far from alone in seeking the contract. Of 65 bids submitted, 62 were from would-be wind energy developers.

Trimont bid wins contract
After two months of reviewing the proposals, Great River Energy — which supplies power to 28 local rural electric utilities with 600,000 members — put the Trimont bid on its short list of finalists. Two months after that, Trimont Wind was selected as the winner.

Of the 50 landowners who joined the LLC, 47 are Minnesota residents, and half are active farmers. More than $500,000 was raised from the members to pay the consultant, legal fees and related costs.

“At that point, we still thought we would own the project,” says Von Ohlen, who is manager of TAWF. What eventually killed that dream was the determination that their LLCcooperative would not be able to use the production tax credits, which can offset a major share of the cost for wind turbines “That ruled out our being the owners.”

Some other ownership options were studied, such as a contract under which ownership would “flip” to the co-op after 12 years. “But we were a little nervous about suddenly becoming the owner of 13-year-old wind turbines, not knowing what kind of shape they would be in at that point. So we instead decided to team up with a major wind power developer.”

Predevelopment work pays off
By doing the predevelopment work, including the always tough job of aggregating the needed land in the right location, and by having the power contract in hand to supply Great River Energy, TAWF was in a much stronger position than landowners typically are to negotiate a strong deal on behalf of its members.

The co-op ultimately opted to enter a contract with PPM Energy, a unit of ScottishPower, based in Scotland, which has more than 1,700 megawatts of wind energy in operation or under construction around the globe. PPM Energy built, owns and operates the turbines.

TAWF not only negotiated land lease payments, but got its members a percent of the gross power revenue generated by the wind farm. As the efficiency of the operation improves, the percent of revenue going to the LLC will also rise, says Von Ohlen. Members will earn a minimum yearly return on their investment of 50 percent.

“By delivering signed leases and a power purchase agreement, we were able to get a much better than average deal,” he says. “The industry standard is for a lease payment of $2,000 to $3,000 per tower, but we were able to get $4,000.”

The wind farm includes 67, 1.5- megawatt turbines, manufactured by General Electric. Each turbine stands 265 feet high from base to hub. About 75 percent of the towers were built in Fargo, N.D., as were most of the blades, Von Ohlen says.

Only minor disruptions to farming
Of the wind farm’s 8,500-acre “footprint,” 8,000 acres are in the LLC. Construction started in May 2005 and was completed within six months. Von Ohlen says only minor disruptions to farming operations were caused by the construction.

The turbines themselves take up very little land, with the biggest space demand being for the 16-foot-wide access roads. “Even if the road is a half mile long, that still equals only about an acre,” Von Ohlen notes. And the access roads can come in handy for farming operations.

The LLC still holds regular board meetings, with its main function being to administer and distribute the payments from the wind farm to its members.

Von Ohlen says a study showed that for this project, the ultimate net return to members will be about the same as had they owned the turbines outright. “The biggest difference is that we will get more of the return in the early years of the project, whereas with direct ownership, more of the returns would have come in the later years,” he explains.

PPM Energy has an option in 15 years to pay a lump sum to TAWF and would then own all the power revenue. In that case, the LLC would dissolve, and from that point on the power company would simply work directly with landowners to pay land lease fees.

The wind farm is expected to generate more than $1 million annually for the local economy through a combination of taxes paid, easement payments and power payments to the LLC.

Great River Energy is putting out a new proposal for another wind farm in the area, and Van Ohlen says a new LLC is being formed to again do the predevelopment work and negotiate a contract on behalf of its members. His family holds land in the new area as well, “so we’ll be involved in both. But they will be separate entities, each with their own boards.”

How is life with so many wind turbines suddenly sprouting up from their corn and soybean fields? “It’s definitely something to get used to when they first go up. But now they are just part of the scenery — you hardly even notice them.”





November/December Table of Contents